Holma solpark
in operation
Almost 20,000 solar panels erected in record time
Holma, Falköping
Holma solar park becomes Aneo's second solar power plant in operation and is one of two ground-mounted solar power plants under construction in Falköping. The solar park has been developed and built in collaboration with the Swedish development company Sunna Group, where Aneo is also a shareholder.
2026
15GWh
13,35 MWp
18 800
About the Project
Holma solar park is built on an area that has been lying fallow for over 20 years. Through the development of the solar park, the area can be utilized again, and with the construction, the power plant is also prepared so that the area can be used for grazing in parallel with power production.
From the investment decision, through the start of construction in spring 2025, to a power plant expected to be in operation by the end of October 2025, it has taken less than a year.